Understand bushfire attack level, how NSW checks bush fire prone land and what BAL can change before you design or quote your new home.

Bushfire attack level (BAL) measures how exposed a home could be to ember attack, radiant heat and direct flame contact. NSW uses six levels (BAL-LOW, 12.5, 19, 29, 40 and FZ), and your block's level sets the construction standard for a new home and whether complying development is possible.

Key facts

  • NSW uses six BAL levels under AS 3959:2018, from BAL-LOW to BAL-FZ.
  • Bush fire prone land can be checked on the Planning Portal Spatial Viewer and identified on a planning certificate.
  • BAL is determined from the area, vegetation, distance to vegetation and slope.
  • Complying development cannot be carried out on land assessed as BAL-40 or BAL-FZ.
  • Bush fire prone land maps must be recertified at least every five years.

Is your block bush fire prone?

Check the NSW bush fire prone land map and your planning certificate before you start design work. These checks identify whether bush fire planning controls may affect the approval path for your block.

The NSW Planning Portal Housing Code identifies the bush fire standards for dwelling houses in clause 3.4. The NSW Planning circular also confirms that mapping is available through the Planning Portal Spatial Viewer and that a bush fire prone property is identified on its planning certificate.

Maps are recertified at least every five years, so use current information when reviewing an established block, a new estate lot or a knockdown rebuild site. A block backing onto a reserve or creek line also deserves an early check.

What are the six bushfire attack levels?

The six levels describe increasing exposure to bushfire attack. The NSW RFS descriptions below help you understand what each bushfire rating means before detailed design and assessment.

BALRisk in plain words
BAL-LOWLowest risk.
BAL-12.5Primarily exposed to embers.
BAL-19Moderate risk from embers and burning debris.
BAL-29High risk from embers, debris and heat.
BAL-40Very high risk, with potential exposure to flames.
BAL-FZExtreme risk, with direct exposure to flames.

These descriptions are from the NSW Rural Fire Service explanation of bushfire risk levels. A BAL is site-specific. Do not assume that neighbouring blocks have the same rating.

How is a BAL assessment worked out?

A council or suitably qualified bush fire consultant determines the BAL using the site conditions. The assessment considers the region, vegetation, distance to vegetation and slope.

What to review first

  1. Check the Planning Portal Spatial Viewer for bush fire prone land mapping.
  2. Review the planning certificate for the property.
  3. Identify vegetation, separation distances and the site's slope.
  4. Confirm the assessment and approval requirements with council or a recognised bush fire consultant.

Raise these checks during your site review, before the house design and quote are developed. Our site review considers frontage, access, orientation, existing conditions and planning constraints so the design direction responds to the block. You can also review the sloping block building guide where slope is one of the site conditions requiring attention.

What does BAL change for a new home?

BAL can change the approval route and the construction standard. It can also affect design details such as windows, decks and roof specifications.

Approval pathway

Complying development is not allowed on BAL-40 or BAL-FZ land. Other complying development standards also apply, including direct public road access and mains electricity, reticulated water or a tank. A development application usually needs a bush fire assessment report under Planning for Bush Fire Protection 2019. Our CDC vs DA guide explains the two approval routes.

Read the NSW Planning circular PS 21-010 for the relevant NSW planning direction on development on bush fire prone land.

Construction and design

Under the NCC's Deemed-to-Satisfy provisions, building work on bush fire prone land follows AS 3959:2018 or the NASH Standard for steel-framed housing. That pathway does not apply in BAL-FZ, or where the development consent sets different conditions.

On blocks that back onto reserves or creek lines, bush fire mapping adds a BAL assessment and can change window, deck and roof specifications. Do not treat BAL as a late selections issue. It belongs in the site review, design brief and approval planning.

What happens on a new estate lot?

A new estate lot may have bush fire information prepared during subdivision. Ask the developer for the Post-Subdivision BAL Certificate before design begins.

In an urban release area, no further section 4.14 bush fire assessment is needed when a bush fire safety authority was issued within the past five years and the Post-Subdivision BAL Certificate shows the land is not BAL-40 or BAL-FZ, provided the relevant conditions are met. Keep the certificate with the project records and confirm that it applies to your lot and proposed work.

What about an extension or knockdown rebuild?

An extension or knockdown rebuild on an established block still needs an early bush fire review, because the BAL can affect both the approval pathway and the construction.

Start by checking the planning certificate, current mapping, vegetation, distance and slope. Then ask council or a recognised bush fire consultant what assessment is required. A block backing onto a reserve or creek line can carry bush fire mapping. As our Castle Hill area page notes, this can change window, deck and roof specifications, and some bush fire and flood categories can push a project towards a development application.

When should BAL be raised with your builder?

Raise bushfire attack level at the site review, before design and before the quote. Early review gives the project team time to identify mapping, certificates, assessment needs and construction requirements.

For a Western or North West Sydney project, bring the planning certificate and any developer documents to the first discussion. Ask whether a Post-Subdivision BAL Certificate exists, whether the block is mapped as bush fire prone land and whether the intended work is a new home, extension or knockdown rebuild. We can then coordinate the site constraints with the design and approval planning.

Frequently asked questions

What does BAL-29 mean?

BAL-29 is a high bushfire attack level. The NSW Rural Fire Service describes it as exposure to embers, burning debris and heat. It is one of six levels used in NSW, and it is determined from site conditions including vegetation, distance to vegetation and slope. Do not use the label alone to choose a design; confirm the site-specific assessment and applicable construction requirements.

Can I use a CDC on bush fire prone land?

Sometimes, but bush fire prone mapping alone does not answer the question. Complying development cannot be carried out on land assessed as BAL-40 or BAL-FZ, and other standards apply, including direct public road access and mains electricity, reticulated water or a tank. Check the planning certificate, BAL information and the applicable NSW Housing Code requirements before relying on a CDC pathway.

How do I know if my land is bush fire prone?

Check the bush fire prone land map in the NSW Planning Portal Spatial Viewer and review your planning certificate. NSW maps are recertified at least every five years, so use current records. Also consider site conditions such as vegetation, distance to vegetation and slope. If the information is unclear, ask council or a recognised bush fire consultant what assessment is needed.

Who does a BAL assessment?

A council or suitably qualified, recognised bush fire consultant can determine the BAL, using the relevant site conditions. The assessment considers the region, vegetation, distance to vegetation and slope. For a new estate lot, first ask the developer whether a Post-Subdivision BAL Certificate exists. Give the assessment or certificate to the design and approval team before the home is documented and quoted.

Does BAL affect an extension?

Yes. An extension on an established block can require bush fire assessment and may affect the approval pathway and construction response. Bush fire mapping can also change window, deck and roof specifications. Start with the planning certificate, current map and site conditions, then confirm the requirements with council or a recognised bush fire consultant before finalising the extension design.

Next step: check the bush fire prone land map and your planning certificate, ask the developer for any Post-Subdivision BAL Certificate, then talk to us about your block before design starts.